The last batch of Chemical Injection Packages leaves for Qatar LNG project

Last week, the last batch of 62 𝗖𝗵𝗲𝗺𝗶𝗰𝗮𝗹𝘀 𝗜𝗻𝗷𝗲𝗰𝘁𝗶𝗼𝗻 𝗣𝗮𝗰𝗸𝗮𝗴𝗲𝘀 left the Fores Engineering workshops for an ambitious energy development project located in Qatar, which aims to increase the country’s liquefied natural gas (LNG) production capacity.

The project is set to exploit the Northern Natural Gas Field, one of the world’s largest non-associated gas reserves.

Although it is a traditional extraction and liquefaction project, its scope includes several measures to reduce the impact of natural gas on the environment, such as carbon capture solutions and solutions to improve operational practices.

Technical details:
➔ ~ 1300 m2 overall
➔ > 800 tons
➔ 3000 documents issued
➔ > 100 suppliers involved including equipment manufacturers, installers, logistics